Local supply feasibility brief

A potential price corridor exists: 77.2–135.0 EUR/MWh. Validate the assumptions with both parties.

Delivered electricity after losses686MWh/year
Residual grid purchases814MWh/year
Buyer annual savings€24,010EUR/year
Seller incremental annual cash€25,100EUR/year
Seller net present value€165,910EUR
Buyer annual savings€24,010 EUR/year
Seller incremental cash€25,100 EUR/year

Before you progress

  • Obtain interval generation and demand records from willing counterparties.
  • Commission a route, easement, electrical and connection assessment.
  • Confirm the national supply structure, permissions and charge treatment with local advisers.
Assumptions & limits
  • All money is entered and reported in EUR; no automatic currency conversion.
  • Pre-tax, unlevered screening with constant annual cash flows; no inflation, grants, financing or terminal value.
  • Country identifies the review jurisdiction; no permit, tax exemption, tariff entitlement or grid approval is inferred.
  • Coincident energy is your assumption. Annual generation and consumption alone do not establish hourly matching.
  • The seller funds the wire. Cable losses are applied once; residual grid purchases and entered retained charges remain payable.
Inputs used in this assessment
countryCZ
currencyEUR
Solar generation1100.0 MWh/year
Wire investment paid by seller100000.0 EUR
Assessment term20 years
Discount / seller hurdle rate7.0 %
Buyer consumption1500.0 MWh/year
Simultaneous supply before losses700.0 MWh/year
Agreed electricity price100.0 EUR/MWh
Existing export price60.0 EUR/MWh
Buyer current all-in price160.0 EUR/MWh
Retained charges on direct supply25.0 EUR/MWh
Wire operating costs1.5 % of investment/year
Cable losses2.0 %

Visitor or partner scenario inputs · PV8 shared finance core · PV8 direct-wire commercial engine dw-economics-v2
Model: partner-screening-v1 · Reference: 6b6423431d3d